The Latest construction update on the Regal Cinema as of 8th October 2026 is copied below:
🧱 *Foundations — complete*
The foundation slab is finished, and so is the new foundation beneath the retained façade. In plain terms: the wall that has stood on this corner since 1935 now has a brand new pair of legs underneath her. Every floor, every beam, the entire new building will sit on what went into the ground these past few weeks. It is the least photogenic milestone we will ever post about, and one of the most important.
She’s now ready for the new structure to rise behind her and brace her.
🏗️ *A crane is on its way*
Next week a crane is being installed on site, standing 25 metres tall. That matters more than it might sound — the crane does all the heavy lifting, and it’s what lets the frame go up quickly. The plan is to build through the winter, so from here on the changes should be visible from the pavement rather than buried in the ground.
Access to the cycle lane will be restricted on the day of installation. Apologies for the disruption; it’s one day, and it buys us a great deal.
⏱️ *Where we are against the programme*
Straight answer: the pause used up a lot of the contingency we’d built into the programme. The good news is we’re now winning that time back faster than we planned. Completing the foundations is the main reason — it takes the slowest and least predictable work off the critical path, and frame erection moves at a different pace entirely.
🎬 *Who will run the cinema?*
The question we get asked most. We’re in discussions with three cinema operators, and the talks are now into the detail — down to who builds and installs what inside the cinema, which has to be settled before a lease can be signed. We won’t name anyone until the ink is dry. When it is, you’ll hear it here first.
✅ *An independent check on how we’re doing*
Last month the site had its first full inspection under the Considerate Constructors Scheme — the independent body that monitors how building sites treat their neighbours. We scored 86%, rated Excellent, with 90% for how we look after the community. The inspector also credited the way we keep neighbours updated — that’s this channel.
🚶 *Safety*
Crane installation and frame erection mean lifting operations, deliveries and heavy plant on site through the day. Please keep to the marked pedestrian routes, and give the site gates a wide berth on crane day. 🚧
📸 Follow the journey on Instagram
www.instagram.com/bar.homes
Thank you, as always, for sticking with us.
With everything we’ve got — The Regal Team ✨
Update as of 13th August 2026
The Highams Park Planning Group (HPPG) are aware that there have been some concerns expressed locally about the progress on the Regal Cinema and the widening of a crack on the façade.
We contacted the owners and asked them to provide an update and as to the progress of the works. Their response is copied below:
Regal Cinema*
Where things stand*
About that “crack in the façade”*
We’re keeping watch, too. A comprehensive monitoring regime was agreed and in place before we even started: fixed points across the façade are checked daily, weekly and monthly. If you’ve spotted one of our engineers at a tripod with surveying kit — that’s exactly what they’re doing. She’s behaving precisely as she should.
Why the pause*
The money question*
A word to Highams Park*
The Regal is coming back. And she’s coming back properly. 
Follow the journey on Instagram