Update on Construction of Regal Cinema

1145

The Latest construction update on the Regal Cinema  as of 8th October 2026 is copied below:
🧱 *Foundations — complete*
The foundation slab is finished, and so is the new foundation beneath the retained façade. In plain terms: the wall that has stood on this corner since 1935 now has a brand new pair of legs underneath her. Every floor, every beam, the entire new building will sit on what went into the ground these past few weeks. It is the least photogenic milestone we will ever post about, and one of the most important.

She’s now ready for the new structure to rise behind her and brace her.

🏗️ *A crane is on its way*
Next week a crane is being installed on site, standing 25 metres tall. That matters more than it might sound — the crane does all the heavy lifting, and it’s what lets the frame go up quickly. The plan is to build through the winter, so from here on the changes should be visible from the pavement rather than buried in the ground.

Access to the cycle lane will be restricted on the day of installation. Apologies for the disruption; it’s one day, and it buys us a great deal.

⏱️ *Where we are against the programme*
Straight answer: the pause used up a lot of the contingency we’d built into the programme. The good news is we’re now winning that time back faster than we planned. Completing the foundations is the main reason — it takes the slowest and least predictable work off the critical path, and frame erection moves at a different pace entirely.

🎬 *Who will run the cinema?*
The question we get asked most. We’re in discussions with three cinema operators, and the talks are now into the detail — down to who builds and installs what inside the cinema, which has to be settled before a lease can be signed. We won’t name anyone until the ink is dry. When it is, you’ll hear it here first.

✅ *An independent check on how we’re doing*
Last month the site had its first full inspection under the Considerate Constructors Scheme — the independent body that monitors how building sites treat their neighbours. We scored 86%, rated Excellent, with 90% for how we look after the community. The inspector also credited the way we keep neighbours updated — that’s this channel.

🚶 *Safety*
Crane installation and frame erection mean lifting operations, deliveries and heavy plant on site through the day. Please keep to the marked pedestrian routes, and give the site gates a wide berth on crane day. 🚧

📸 Follow the journey on Instagram
www.instagram.com/bar.homes

Thank you, as always, for sticking with us.
With everything we’ve got — The Regal Team ✨

Update as of 13th August 2026
The Highams Park Planning Group (HPPG) are aware that there have been some concerns expressed locally about the progress on the Regal Cinema and the widening of a crack on the façade.

We contacted the owners and asked them to provide an update and as to the progress of the works. Their response is copied below:

*🎬 Regal Cinema*
Hello Highams Park — sorry for the recent radio silence. 👋
Truth is, we don’t want to post until we had something solid to tell you. Now we do — so here’s all of it.
*🏗️ Where things stand*
With enabling works, site set-up, demolition and the façade retention now behind us, we’ve been quieter on site while we finalise some important design work. As we’ve dug down, we’ve uncovered three or four different types of old foundations from the building’s past lives — a common find beneath a structure this old, but the new foundation design has to respond to what’s actually in the ground, not what the old drawings suggested. On a project of this scale, the unglamorous work happening at the drawing board right now is what makes sure everything that follows is done once, properly, to the highest standard.
*🧱 About that “crack in the façade”*
There’s been a lot of chatter on social media, so here are the facts. Before works began, our structural engineers surveyed the retained façade and identified several cracks. In a brick wall standing on London clay, on a corner the Regal has occupied since 1911, that is entirely expected — she’s seen a lot of Highams Park life. Our structural engineer — 45 years of post-qualification major-project experience — inspected everything thoroughly and adapted the design where required as works progressed. We sprayed a new 8-inch (200mm) reinforced concrete wall, using a technique called shotcrete, directly against the back of the original brick wall — permanently bonding the two into one single, unified structure. In plain English: the old brickwork no longer carries the load alone. It has a reinforced-concrete partner bonded to its back, holding it stable — which is what allowed us to safely demolish the remainder of the building behind it, with additional temporary propping added as an extra safeguard. The result is a wall that is stronger, safer and more durable than she has ever been. The soul of the Regal, with a serious backbone to match. 💪 We’re keeping watch, too. A comprehensive monitoring regime was agreed and in place before we even started: fixed points across the façade are checked daily, weekly and monthly. If you’ve spotted one of our engineers at a tripod with surveying kit — that’s exactly what they’re doing. She’s behaving precisely as she should.
*☀️Why the pause*
Since May we’ve had a run of extreme heat, and you cannot pour structural concrete above 32°C without compromising its strength — we won’t bake weaknesses into foundations meant to last another century. The same heat is punishing for the people on site, and stop-start working in those conditions is inefficient and unfair on them. So we took a planned pause: our design team is using it to complete the next-phase design around the new ground information, and our site teams have kept working elsewhere so they return fresh and at full strength the moment temperatures allow. We’ll post here the moment they do.
*💷 The money question*
The project is fully funded. We have already invested more than half of the total project cost — our own money, already in the Ground. We are fully committed, financially and emotionally, to delivering the Regal. So whatever you may read elsewhere — sorry, but we’re not going anywhere!
*💛 A word to Highams Park*
We know how much this building means to you. We see the messages, we see people stop and look through the hoarding, and we feel the weight of what the Regal represents here. Every decision we make is made with care for this neighbourhood in minds. And if anyone understands waiting for something worth waiting for — England fans have been at it since ’66, coincidentally around the time our Chairman first settled in London. We have every intention of the Regal not testing your patience anywhere near that long. 😂 The Regal is coming back. And she’s coming back properly. 🎬
📸 Follow the journey on Instagram
and thank you, genuinely, for your patience and your belief in this project. It means more than you know.
With everything we’ve got — The Regal Team ✨